Proposed Solutions for a Solar-Powered Air Conditioning System

Proposed Solutions for a Solar-Powered Air Conditioning System

For the Third Floor of the University’s Physical Therapy Building

  1. Introduction

This report presents the technical study and proposed solutions for providing a hybrid solar (ACDC Hybrid) air conditioning system to operate the top floor of the university’s Physical Therapy building, using fifteen (15) air conditioning units, each rated at 5 HP.

A field survey of the building’s roof designated for solar panel installation was carried out. The survey showed that the existing roof is constructed of wood and cannot bear the structural loads resulting from the installation of the solar panels and their outdoor units. This required two alternative technical solutions, detailed in full within this report.
 

  1. Scope of Work
  • Supply and installation of fifteen (15) split air conditioning units rated at 5 HP, operating on a hybrid solar/electrical system.
  • Supply and installation of the required solar panels (2 to 9 panels per AC unit, depending on the load).
  • Execution of the structural works required to support the panels according to the adopted solution.
  • Running the necessary electrical (DC/AC) cabling to connect the panels with the units.

 

  1. Technical Specifications of the Proposed AC Units

The table below shows the full technical specifications of the proposed hybrid air conditioning unit family. The model adopted for this project is KFR-90GW/BPSA (5 HP), highlighted in light green in the table:

Model Cooling Capacity Heating Capacity Cooling Power Input Heating Power Input Net Weight (Indoor/Outdoor) kg
KFR-26GW/BPSA 9000BTU 9500BTU 100-1200W 120-1200W 9.6 / 39
KFR-35GW/BPSA 12000BTU 19000BTU 110-1500W 130-1510W 9.6 / 40
KFR-50GW/BPSA 18000BTU 19000BTU 140-1800W 200-1900W 12.5 / 44
KFR-70GW/BPSA 24000BTU 25000BTU 240-3030W 260-3140W 15.2 / 62
KFR-90GW/BPSA (5 HP) 30000BTU 31000BTU 280-3350W 300-3450W 15.2 / 62
KFR-100GW/BPSA 36000BTU 37500BTU 320-3510W 350-3650W 15.2 / 73

Note: All models operate on a 220V (50/60Hz) AC supply and can accept a DC input of up to 380V, allowing a direct connection with the solar panels without the need for a power inverter.
 

Figure (1): Original technical specification sheet supplied by the manufacturer

 

  1. How the Hybrid System Works (ACDC Hybrid System

Figure (2): Illustrative diagram of the hybrid system operation (Source: manufacturer’s data)

 

  1. Site Survey Findings

The field survey of the Physical Therapy building’s roof showed that the existing roof is constructed with a wooden covering (as shown in the two attached photos), and it is not structurally qualified to bear the additional loads resulting from installing the solar panel mounts and their weight. This requires implementing one of the structural solutions described below before proceeding with the installation works.

Figure (3): Current roof of the Physical Therapy building during the survey

 

Figure (4): Details of the wooden covering of the building’s roof and its current structural condition

 

  1. Option 1: Structural Reinforcement of the Physical Therapy Building Roof (Higher Cost)

This solution addresses the wooden roof’s inability to bear loads through one of the following two alternatives:

  • Pouring a reinforced concrete slab to replace the current wooden roof, providing a solid structural base capable of bearing the weight of the panels, their mounts, and the outdoor AC units.
  • Or constructing a steel framework above the building’s main columns, with the bases tied together according to the required area, ensuring safe load distribution without affecting the building’s structural safety.

This solution has the advantage of installing the panels and AC units entirely above the Physical Therapy building itself, which shortens the electrical cable routing. However, it requires additional structural works (concrete/steel), which increases the overall project cost and execution time compared to Option 2.
 

  1. Option 2: Installing the Panels on the Nursery Building and Running Cables to the College (Lower Cost)

This solution relies on installing the solar panels on the roof of the adjacent nursery building (shown in the attached photo), whose structural roof is expected to be suitable to bear the loads without any additional reinforcement, and then running DC feeder cables from the panel location to the AC units at the college building (Physical Therapy building).

Figure (5): Aerial view of the nursery building proposed for the solar panel installation

This is the lower-cost and faster-to-execute solution, as it requires no structural works at the level of the Physical Therapy building’s roof. The work is limited to preparing the panel mounts above the nursery building and running the necessary cabling between it and the college building, considering the technical standards for cable length and voltage-drop percentage.
 

  1. Technical Comparison Between the Two Options
Comparison Aspect Option 1: Reinforced Concrete/Steel Above Existing Roof Option 2: Panels on the Nursery Building
Current roof condition Requires a full structural modification of the existing wooden roof No intervention needed on the Physical Therapy building roof
Structural works Reinforced concrete slab or a steel structure above the main columns, with bases tied together Not required – the nursery roof is used as-is after confirming its load capacity
Cable routing Short (panels above the same building) Longer – requires running DC cables from the nursery building to the college building
Estimated cost Higher Lower
Execution time Longer (structural works + installation) Shorter (direct installation + cable routing)
Impact on building operation May require partial shutdown during concrete/steel works Minimal impact on the building’s daily use
  1. Technical Recommendation
  • If a higher budget is available and it is preferred to keep the panels directly above the Physical Therapy building, Option 1 (structural reinforcement with concrete or steel) is recommended.
  • If the priority is to reduce cost and speed up execution, Option 2 (installation above the nursery building with cable routing) is recommended, subject to prior confirmation that the nursery roof can bear the loads.